Foreshore Lake Macquarie Update
June 3, 2020
Foreshore Lake Macquarie has made significant progress in the structure over the past two months with the completion of blockwork to the lower levels, and ground floor suspended concrete slabs. The structure has continued to move upwards with majority of the Level 1 suspended concrete slabs also being poured.
In June, Level 2 structures in each building will be poured which will allow for the removal of formwork supports in the lower Levels. The removal of formwork will enable the contractor to commence the construction of the external façade leading to the fit out of apartments on the lower ground floor. Topping out of the structure is still on track for the end of July, marking a major milestone for the project.